Fillauer Branch phases set target dates; adjacent property owner backs VFW–Weeks extension
Summary
Staff set 9/1/2026 target completion dates for Fillauer Branch Phase One and Phase Two; a property owner identified as Presswood told committee member Kevin Raper he supports a proposed extension across his land from the VFW to Weeks.
Get email alerts on the Right Of Way topic
No spam. Unsubscribe anytime.
Staff provided schedule targets for Fillauer Branch construction phases: Phase One (Blythe Ferry to Westview) and Phase Two (Spring Creek to Elm) are both listed with target completion dates of 9/1/2026. Those dates frame near-term construction and coordination work.
Committee member Kevin Raper reported that a property owner adjacent to the VFW, identified as Presswood, approached him and expressed support for a trail extension crossing that property from VFW to Weeks. The owner's favorable position may reduce a potential barrier to that segment but does not replace any formal easement or permit process.