Shawnee County to replace timber bridge; Jackson County to pay $49,695.60 share
Summary
Shawnee County presented plans to replace a timber-span bridge near 94th just east of I Road; Jackson County is responsible for 6.3% of costs, an estimated $49,695.60. Officials said construction would likely begin in 2027 and could take 90–100 days.
Get email alerts on the Bridge 94th I Road topic
No spam. Unsubscribe anytime.
Shawnee County Public Works Director Curt Niehaus and Engineer Michael Welch described plans to replace a timber-span bridge near 94th just east of I Road and said the structure should have a 75–100 year service life with minimal maintenance. Jackson County's portion of the estimated cost was stated as 6.3%, or $49,695.60.
Commissioners asked whether the project could use large culvert tubes rather than a full bridge when drainage allows; Welch said tubes are used where drainage and site conditions permit. Officials also noted that one residential property would be cut off from direct access during construction and discussed building a temporary 'shoofly' access road, with an estimate from a contractor of $25,000–$30,000 to make minimum-maintenance roads drivable during work. County Counselor Todd Luckman will review the intergovernmental agreement at the next meeting.