Council OKs $3.99 million Phase 1 of Coyote Ridge Park with emphasis on ADA and inclusive play

Castle Pines City Council · November 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council unanimously approved Resolution 24-60 to move forward with Phase 1 of Coyote Ridge Park improvements, a design-and-bid effort with a budget estimate of $3,997,217 that prioritizes ADA access, inclusive playgrounds, connectivity and a pollinator garden; staff will seek design services and prepare construction documents.

The Castle Pines City Council voted unanimously to approve Resolution 24-60 to proceed with Phase 1 improvements at Coyote Ridge Park, an expansion and redesign project that emphasizes accessibility and inclusive play.

Consultant Mia Ricketsons of Fort Copeland Macht presented the Phase 1 plan and a cost estimate, saying the phase "kind of culminates into a little under 4,000,000." The presentation detailed ADA-accessible walkways to picnic structures, an expanded inclusive playground with separate areas for ages 2–5 and 5–12, improved surfacing (synthetic turf or inclusive play surfacing), additional bike racks, maintenance access, a potential pollinator garden with deer-resistant species, and a fence along the south side of the basketball courts to reduce balls rolling into drainage areas.

Ricketsons delivered the project budget estimate as $3,997,217 and noted final extents will depend on site survey, construction documents and escalation. Council discussed fence height and material (6 feet, likely black-vinyl-coated chain link was proposed), which existing areas would be included in Phase 1, and a broader master-plan estimate for the full park of about $17 million. City staff said the next steps are to develop a scope for design services, produce base construction documents for public bidding, and return to council with a contract recommendation.

Council members praised the consultant work and the Parks & Recreation Advisory Board’s focus on inclusivity. The resolution passed with all members present voting in favor.