Council reviews road-project buckets; staff to seek county participation for Monarch Boulevard improvements
Summary
Staff presented a multi-bucket road plan for 2025 (local maintenance, Happy Canyon interchange design work, Monarch Boulevard improvements). Monarch (Glen Oaks to Winterberry) was estimated around $4.5M; staff said the city will request county partnership for a portion of costs and will study roundabout vs. signal at Buffalo/Monarch.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Road projects were a major policy topic in the study session. Staff presented three buckets of road work for 2025: local maintenance priorities, continued design for the Happy Canyon interchange (consultant work with Jacobs) and a proposed Monarch Boulevard project (Glen Oaks to Winterberry) estimated roughly at $4.5 million.
Staff said the Monarch project could change if a roundabout is warranted at Buffalo Trail and Monarch instead of a signal; a traffic-engineering study in the contract scope will determine whether a roundabout or signal is appropriate and will affect the cost estimate. Staff said the city intends to ask the county to partner on a share of the Monarch costs, historically seeking county participation for arterial improvements. Council members urged careful coordination with county staff, the metro district and project timing to avoid overlapping major asks.
No formal council pledge of county ask amounts was finalized in the study session; staff said they would pursue coordination with county staff and report back to council with a recommended funding request and updated cost estimates.