County to seek bids for new First Tee clubhouse; staff cites building decay and program usage
Summary
Staff asked permission to advertise bids for a ~2,000 sq ft replacement clubhouse for the First Tee program, citing a rotting crawlspace and steady program use (staff and the program estimated 250–300 kids served annually).
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
County staff requested approval to move forward with a hard‑bid solicitation to construct a roughly 2,000‑square‑foot replacement clubhouse for the First Tee program behind the Mike Daniel Recreation Center.
A First Tee representative told commissioners the program serves roughly 250 to 300 kids a year and draws players from the city, county and surrounding counties. "We service within the program, we service about 250 to 300 kids a year," the representative said. Staff described the existing clubhouse as a converted house with a waterlogged crawl space and recommended building a comparable stick‑built facility on an adjacent pad so the program can continue operations during construction.
Staff estimated construction costs in the mid‑$200,000s before bonding and noted state law requires payment and performance bonds on projects above the bonding threshold; the board agreed to take the item up at the evening meeting for formal action.