Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Historic Preservation topic

No spam. Unsubscribe anytime.

Commission reviews three cost estimates to stabilize and renovate former Lehi Inn

Riverfront Improvement Commission · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff presented three options and cost estimates for the municipal end (former Lehi Inn): stabilization at about $91,000, a concessions/amenity build at roughly $285,000, and a full historic renovation near $436,000; commissioners discussed sewer, flood mitigation and fundraising approaches.

Staff reviewed three options and corresponding cost estimates for the former Lehi Inn and asked the commission to decide an approach to fundraising and city involvement. "The first one is stabilizing the structure so that it doesn't worsen and get demolished by neglect," said staff (S4), who identified that the minimal stabilization option totals roughly $91,000, the midrange concessions option about $285,000 and the historically accurate renovation around $436,000.

Commissioners asked whether sewer connections, concrete apron repairs and flood-resistant finishes were included in the estimates; staff said the estimates include adding a sewer line where none currently connects and that the Main Street Landing restroom project may mitigate some needs. Debate focused on optics and fundraising strategy: several commissioners favored pursuing the historic renovation as a fundraising target to access preservation grants and generate public excitement, while others urged caution given the $500,000 target and recommended phasing. The commission ultimately voted to pursue fundraising for the historic renovation (option 3) and set a working target that assumes the city will cover stabilization costs.