Commissioners recommend extending CUP time limits to two years to ease post‑COVID delays
Summary
After discussing repeated delays in projects since COVID and concerns about concentrating authority in staff, the commission amended and recommended ordinance 2026‑12 to extend conditional‑use permit time limits from one year to two years so stalled projects will return to the commission if not completed.
Get email alerts on the Conditional Use Permit Timeline topic
No spam. Unsubscribe anytime.
Kane County staff told the commission that many conditional‑use permits have stalled in recent years and proposed giving staff authority to extend time limits; commissioners decided instead to recommend extending the CUP time limit from one to two years so stalled projects return to the commission if they remain incomplete.
"I think a lot of them are struggling anymore...it seems a lot of them are taking 4 years to get off the ground lately," Shannon said, describing projects that have taken longer to achieve permits and construction since the pandemic. Commissioners expressed competing priorities: some favored administrative flexibility to ease applicants' burden, while others warned against concentrating too much decision‑making power in a single staff position.
After discussion the commission approved an amendment to the ordinance to change the timeline to two years (instead of an administrative transfer of authority). The body moved and seconded the amended recommendation and the motion carried; the ordinance will be forwarded to the County Commission.