Trail phase 2 and Highway North improvements advance with grants, staff says

Shelton City Council · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported a likely $275,000 award for phase 2 of the Crosstown Trail, said Highway North design is approaching 60% with construction expected next year, and noted coordination with transit and WSDOT for interchange and bus-stop improvements.

Staff said the city expects a notice of award for phase 2 of the Crosstown Trail for about $275,000 and noted the project is at roughly 60% design. Separately, Highway North improvements — from C Street to the Plaza intersection — are approaching 60% design and are targeting construction next year; staff emphasized coordination for pedestrian and bicycle accommodations.

The presentation noted a focus on shovel-ready projects to improve competitiveness for grant funding and described efforts to work with WSDOT and transit agencies on interchange improvements and bus-stop relocations to avoid blocking intersections. "If you recall, Jordan's kind of leading some of those efforts ... We're at 60% on phase 1, and, we will be starting phase 2 as soon as we get the award," a staff speaker said.