Causeway elevation and road resurfacing studies flagged as priorities for resilience
Summary
Council reviewed an LCOG feasibility study on causeway elevation and prioritized road resurfacing for Town‑owned streets; SCDNR interest in restoring Scott Creek flow and SCDOT assessment were discussed as part of causeway options.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council discussed vulnerability of the causeway to flooding and storm surge and noted the Lowcountry Council of Governments (LCOG) feasibility study that includes elevation options and cost estimates. Council Member Robert Renner, who represents Colleton County on LCOG, said the report includes options and cost estimates. The minutes note SCDNR had earlier expressed interest in restoring flow to Scott Creek as part of the project, but SCDOT concluded restoring flow would not provide significant advantage for the causeway effort.
On local streets, Town Administrator Mark Aakhus reported he has asked the Town’s engineer to prioritize town‑owned roads for resurfacing and said cost estimates will be sought. Funding options, including potential Colleton County Transportation Committee (CTC) support, will be considered as part of planning.