Rockwall County staff report timelines for FM 549, Crenshaw Road and other corridor projects
Summary
County project staff gave detailed updates on multiple road projects: FM 549 construction completion moved to January 2029, Crenshaw Road contract approved with preconstruction and anticipated start 08/10/2026, and several PSAs and MOUs are scheduled for upcoming commission and RTC consideration.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
A county project staffer briefed the consortium on the status of multiple highway and road projects across Rockwall County. The update covered updated construction timelines, design activities and coordination with TxDOT and regional partners: the FM 549 anticipated construction completion date was updated to January 2029, several project design tasks and right‑of‑entry actions are underway, and agreements such as a PSA for FM 1141 and an MOU with the RTC are scheduled for consideration by county commissioners and the regional transportation commission.
The staffer listed milestones and near‑term dates: a preconstruction meeting for the Crenshaw Road contract (approved June 23) is being scheduled and construction is anticipated to start on 08/10/2026; public outreach and environmental reports are advancing in coordination with TxDOT; and a public meeting for one corridor is expected in fall 2026. "FM549, the anticipated construction completion date has been updated to January 2029," the staffer said. Consortium members asked questions about public hearing timing, environmental approvals and how project sequencing might affect local traffic and emergency access. Staff said they will continue monthly coordination meetings and circulate materials to member jurisdictions.