Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

District official reports turf and field projects progressing, cites septic lines and weather delays

Calhoun County Board of Education · February 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Dr. Dowdy told the board the district has completed most of a 12-field athletic upgrade program but some projects (Weaver, Wellborn, Pleasant Valley) faced delays because of unknown septic lines, unsuitable soils and recurring rain; turf installation timetables and cleanup obligations were noted.

Dr. Dowdy gave a detailed update on stadium and field projects across the district, saying crews have completed most of the 12 scheduled field upgrades and remain on target to finish key projects ahead of graduation priorities. He reviewed site-specific issues — unexpected septic lines in outfields, unsuitable soils requiring trucking of fill, and frequent rain that has delayed dirt work — and described the contractor cleanup and installation schedule.

On project specifics, Dr. Dowdy reported crews had to truck fill into Wellborn and that Weaver’s baseball/softball construction was delayed after crews discovered septic lines in the outfield. "We did not know that there were septic lines in the outfield of those 2 fields," he said, explaining the rework and rerouting required. He told trustees turf installation typically takes a few days once the base work is complete and said the district will hold contractors accountable for cleanup and punch-list items.