Board hears progress on high-school CTE and bid-pack construction

Boyne City Public Schools Board of Education · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District project teams reported design-development progress on high-school CTE additions, a restaurant/teaching kitchen, lighting bids and bleacher logistics; presenters said value engineering reduced square footage to control costs and remain on schedule for fall instruction.

District construction consultants (speakers 9 and 14) updated the board on several bid packs for the high-school renovation and CTE additions. Bid Pack 1 site logistics and bleacher delivery are proceeding; Bid Pack 2 (lighting) is out for bid with a due date in late February and will return to the board with a recommendation in March; Bid Pack 3 includes the culinary/restaurant teaching space and other CTE changes that the team has value-engineered to reduce square footage and cost.

Presenters showed recent elevations and renderings and said the design-development (DD) set is moving toward a near-final 90+% design in mid‑March, with further professional renderings to follow. Board members praised the drawings and asked about schedule and pricing; presenters said they had received favorable feedback so far and expected to remain on schedule for September instruction.