Construction packs on track for high school athletics, renovations and additions, district told
Summary
District project manager Evan reported Pack 1 (athletics) is in submittal, Pack 2 (renovations/lighting) drawings are due this month for bidding, and Pack 3 (additions) is in schematic design with progress on schedules.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Evan provided a facilities update on a multi-phase high school project. He said Pack 1 (the athletics package) is in submittal and remains scheduled for a summer start, Pack 2 (renovations and lighting) will have drawings later this month to go to bid, and Pack 3 (additions) is in schematic design with French's design team and on track for the next design phases.
"So right now, working on the pack 1 submittals," Evan said, adding that the team is extracting as much information as possible from schematic drawings before moving into design development and construction documents. Board members asked whether there were any surprises; Evan responded that they are working through clarifications in the schematic design but are "on the right track."