Estacada wastewater project remains on track; generator part recall expected in September
Summary
City staff said wastewater treatment construction remains on schedule for substantial completion in November next year despite a recent one-week delay on a building and a generator part recall; staff also cited a worker injury last fall but said contingencies have been manageable.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City staff updated the council on wastewater facility construction, reporting that crews began work nearly a year ago and that substantial completion remains planned for November of next year. Staff said concrete forms have been removed on the MBR building and that crews aim to pour two walls a week for the next month or two.
Staff acknowledged a one‑week delay on a particular building due to coordination issues with engineering and suppliers, but said they expect to make up the time. They also reported a recalled generator component (a pin) and said replacement parts are expected to arrive in September so the vendor can perform on-site replacement.
The presentation noted an employee injury last fall as a major challenge, but staff said the employee is expected to recover and that contingency spending has not been excessive. Staff flagged typical construction risks, such as archaeological finds during earthwork, but said overall progress is steady and they will continue to report schedule and budget updates to council.
Councilors asked about the likelihood of early completion and were told the project is roughly one-third of the way through the 30% construction milestone and that early completion is unlikely at this point, though staff remain optimistic about keeping the schedule.