Brickyard Passive Park pre-construction under way; $2.5M grant plus possible private donation
Summary
Contractors for the Brickyard Passive Park are preparing to mobilize; the project is funded by a $2.5 million State Strategic grant and staff said an additional private donation of about $900,000 may be forthcoming.
Get email alerts on the Brickyard Passive Park topic
No spam. Unsubscribe anytime.
A pre‑construction meeting has occurred for the Brickyard Passive Park and the contractor plans to mobilize within weeks to perform limited tree clearing and trail cut‑ins, with work timed to Indiana bat protections. Asst. Dir. Jon Bellack said the contractor will clear trees needed for trail construction and expected substantial completion is toward the end of September 2026.
Dir. Matt Hiscock briefed funding sources for the passive‑park work, saying it "would be paid for through the one‑time State Strategic grant dollars that the City already received in the amount of $2,500,000." He added there is "a potential of an additional $900,000 to come from a private donation" that could increase available funds for trailheads and restrooms. Engineering staff noted a trailhead near Chelley (Mt. Eaton Estates) and said work will minimize neighborhood disruption; parking for trailheads will be provided at the trailhead locations to avoid using residential streets.
Staff emphasized coordination between remediation and passive‑park contractors because the property is large and both crews will operate concurrently. No formal vote was taken; staff will return with progress updates.