Board transfers $75,000 to finish Avon High partial roof replacement

Board of Finance · June 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facing higher-than-expected bids, the Board moved $75,000 from a completed Pine Grove School project to cover a shortfall and allow the Avon High partial roof replacement to proceed this summer.

The Board of Finance approved a transfer of $75,000 from the completed Pine Grove School notification alarm project to the Avon High School partial roof replacement to cover a bid shortfall and allow work to proceed this summer.

Finance Director Tom DiStasio said FY25 and FY26 appropriations together left about $480,000 for the roof work, but bids came in near $544,000 leaving a shortfall (about $64,000). To avoid delaying the project into another fiscal year and facing higher costs, the board approved transferring $75,000 from the completed Pine Grove project. On a motion by Cathy Salchert, seconded by Carl Gisnarian, the motion carried with all voting in favor.

The transfer was framed as a timing and cost-avoidance measure; the finance director said completing the work this summer would prevent further inflation of construction costs.