Construction timeline: rock placement starts in August; in‑water window runs July 16–Feb 15

City of Ocean Shores · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Corps staff said stockpiling began in July, rock placement on the jetty will begin in August, in-water work below the high-tide line is restricted to July 16–Feb 15 each year, and the project is expected to continue through 2029 with restoration into 2030.

Corps staff described sequencing and regulatory timing for the North Jetty maintenance. They said stockpiling and truck deliveries have begun and that placement onto the jetty is scheduled to start in August; some work is constrained by an annual in-water window.

"Stone placement on the jetty will start in August," Gabby Cioppini told the meeting. She also said the in-water work window is July 16 through Feb. 15 in any given year; above-high-tide work such as stockpiling can be done outside those dates. Corps staff said the contractor's schedule includes weather-day buffers and that work is expected to continue through 2029 with site restoration taking about a year afterward.