Engineering update outlines major street projects and streetlight master plan
Summary
Assistant City Engineer Chad Anderson presented an engineering update describing pavement-condition analysis, a Streetlight Master Plan due Fall 2026, and project timelines for 8000 West, 7200 West, Main Street and multiple sidewalk and lighting projects.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Assistant City Engineer Chad Anderson presented the Engineering Update on April 28, detailing a pavement condition analysis and a Streetlight Master Plan that staff said is "Expected to complete in Fall 2026." The presentation listed active projects including the 8000 West widening (curb, gutter, sidewalk, turn lanes; acquisitions nearly complete), two 7200 West reconstruction segments shared with West Valley City, and punch-list work remaining on Main Street construction.
Anderson noted contract and coordination items that are on the critical path: UDOT contract approvals for 7200 West segments, environmental clearance for the 2700 South realignment at 8000 West, and long-lead streetlight materials delaying some lighting work. The slides announced an awarded contract for 9100 West (Main Street to 2820 South) with contract approval slated for May 14 and immediate post-approval mobilization.