How the 4100 South extension will be paid for: state funds, prior appropriations and developer escrow
Summary
The packet breaks down financing for the road: $1.8M state appropriation secured in 2025, up to $3.0M authorized in 2026, and a $750,000 escrow from D.R. Horton to cover overruns; the City will reimburse D.R. Horton on a cost‑reimbursement basis as invoices are submitted.
Get email alerts on the Project Funding topic
No spam. Unsubscribe anytime.
Magna's Agreement with D.R. Horton details the funding structure for the 4100 South extension. The parties record $1.8 million in state appropriations secured earlier and the City requested up to $3.0 million in 2026; together those amounts are referred to in the Agreement as potential State Funds. The Agreement also requires D.R. Horton to deposit $750,000 into escrow to be used for cost overages above the state funding baseline.
The Agreement specifies reimbursement mechanics: up to $3.0 million is to be disbursed on a cost‑reimbursement basis prior to July 1, 2026, with additional reimbursement up to $1.8 million thereafter. If the final cost exceeds $4.8 million, the Agreement provides for reimbursement from the Escrow Funds for amounts up to $750,000 and defines how any remaining escrow will be split. The packet notes the Legislature made up to $3.0M available for the project on March 7, 2026.