Council approves $21,710 increase to finish 2024 street project after contractor cuts scope
Summary
City engineer told council supplier discounts were lost after the contractor reduced its awarded scope; council approved a $21,710 increase so the current contractor can finish two sections of the 2024 street improvement project rather than rebid.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The city engineer told the council that a contractor handling sections B and D of the 2024 street improvement project asked for a $21,710 increase after supplier discounts were lost when the contractor's awarded scope was reduced. The engineer explained the requested increase on a $1,225,000 project and recommended council consider the contractor's previous workmanship before making a decision.
Council members weighed the risk of rebidding โ which could raise costs further or delay completion โ against paying the requested increase. One council member said denying the increase could mean no work this fall and potentially higher costs next year. The council voted to approve the $21,710 increase, 5-0, and staff said the contractor expects to execute the contract and complete the work this fall.