LACSD staff outline CIP progress and plan to phase out asbestos-concrete pipeline
Summary
Engineering and field operations staff reported on capital improvement projects and system condition: the Highland Sewer Replacement and Village Replacement Lines projects are complete, and the District plans to phase out AC pipe (about 65% of system). Staff noted three Q3 water-main leaks, 338 feet of sewer pipeline replaced, and potential future replacement at the Golf Course AC main.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Engineering Technician Gus Albarran updated the board on the District's Capital Improvement Program, reporting that Highland Sewer Replacement Project No. 214 and the Village Replacement Lines Project are complete, and other projects (Corporation Yard Project No. 253; SCADA room Project No. 228; Well #5 Rehabilitation Project J10) remain in progress.
Field Operations Manager Nathan Porter reported that approximately 65% of the distribution pipeline is asbestos concrete (AC). Staff said visual inspections often show imprints still present on AC sections and that the District plans to phase out AC segments over time. Porter noted Q3 included three water-main leaks (with other leaks in service lines, hydrants and laterals) and that 338 feet of new sewer pipeline was replaced; he identified the Golf Course AC main as a likely future capital project candidate.
Porter summarized system condition and emphasized competing mandates that require balancing priorities when scheduling replacements.