Board approves $407,112 change order to add Goshen Township work to 2026 resurfacing contract

Clermont County Board of Commissioners · July 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A change order with John R. Jurgensen increased the 2026 resurfacing contract by $407,112.63 to $4,152,899.69 to add Goshen Township alternate work after the township received Ohio Public Works Commission funding.

County staff presented a recommendation to authorize President Bonnie J. Bachelor to execute Change Order #1 with John R. Jurgensen for project RS-01-26, the 2026 road resurfacing program. The change order adds Goshen Township alternate work and represents an increase of $407,112.63, producing a total adjusted contract price to date of $4,152,899.69. Staff said the work was included as an alternate in the bid and could not be added until Goshen Township received Ohio Public Works Commission funding on July 1.

The board moved, seconded and approved the measure by roll call. Staff confirmed that the change order incorporates previously bid alternate work and is contingent upon release of the required purchase order.