Engineer: temporary repairs could reopen Pudding Hill Road Bridge; town to check permits and FEMA rules
Summary
Ruggles Engineering said Pudding Hill Road Bridge beams remain on abutments and a temporary fix (sheet steel and backfill) could reopen the bridge; the engineer offered to oversee repairs at $100/hour while the town checks permits and potential FEMA reimbursement rules.
Get email alerts on the Bridge Repair topic
No spam. Unsubscribe anytime.
Nate Sicard of Ruggles Engineering told the Select Board he inspected the Pudding Hill Road Bridge and believes it "could be re-opened quickly." He reported that the visible hole is a backwall problem, the beams remain on the abutments, and the concrete degradation is likely the result of salt and low-quality concrete. Sicard recommended placing a 1/4" sheet of steel and backfilling as a short-term repair and offered to oversee work at a rate of $100 per hour.
Town staff and board members expressed concern about performing temporary repairs before a federal declaration and whether FEMA would reimburse work done prior to a declaration; they agreed to consult FEMA contacts and the State Flood Recovery Officer about reimbursement rules and to coordinate with the contractor and excavator operator about site access and permits.