Bristow authority approves more than $284,000 in wastewater-plant construction payments
Summary
The Bristow Municipal Authority approved payments tied to WWTP construction: Holloway, Updike & Bellen $9,350; Aqua-Aerobic System $75,273.76; KBC Construction $200,245.05; several of these were paid from an OWRB loan, the Authority approved the consent agenda by roll call.
Get email alerts on the Wwtp Construction topic
No spam. Unsubscribe anytime.
At its June 16 meeting the Bristow Municipal Authority approved multiple vendor claims associated with wastewater-treatment-plant (WWTP) construction and authorized payments that the minutes indicate were paid from an OWRB loan.
The consent agenda listed Claim #20906 to Holloway, Updike & Bellen, Inc. for $9,350.00; Claim #20907 to Aqua-Aerobic System, Inc. for $75,273.76; and Claim #20908 to KBC Construction, Inc. for $200,245.05. The minutes record those payments as paid from the OWRB loan. Combined, the three WWTP claims total $284,868.81. The consent agenda motion passed on a roll-call vote (Church Aye; Deshazo Aye; Fletcher Aye; Groom Aye; Johns Aye; Witty Aye).
The consent agenda also included routine items: approval of maintenance claims for $66,829.47, unpaid claims $549.19, actual payroll $19,610.76 (pay period ending June 6, 2025), estimated payroll $20,171.62 (pay period ending June 20, 2025); and a budgeted transfer of $50,000 from the Municipal Authority General Fund to the City General Fund. Blankets P.O.s were included (Green Environmental and USPS) with not-to-exceed amounts recorded in the minutes. The Authority did not provide additional discussion in the transcript about the WWTP project scope or schedule during this meeting.