Wastewater supervisor warns clarifier may need full replacement at roughly $500,000
Summary
Town wastewater supervisor reported a clarifier failure and said temporary repairs cost about $5,500, but full replacement of the clarifier interior could cost around $500,000. The supervisor said the town shares about $1,000,000 in reserves with Eastern Roach for such projects and will provide a forthcoming report with options.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The town’s wastewater supervisor (S8) told the council that the plant—constructed in 1995 and online in 1997—is showing age-related problems. After a clarifier failed and required a temporary $5,500 repair, the supervisor warned "it's looking like it's ready for a total replacement in the near future, which you're talking about a $500,000 to replace clarifier, the inside of clarifier." The supervisor said many components (rotors, valves) are original and that staff will send a report outlining options.
S8 noted roughly $1,000,000 in jointly funded reserves shared with Eastern Roach and suggested the town could consider a smaller project to address multiple items rather than spending the full amount at once. Council asked for the forthcoming report and no vote was taken this evening.