Pollard Mills Phase 4 nearly complete; project under budget by roughly $39,000

City of Ashland Board of Commissioners · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Pollard (Polar) Mills Phase 4 infrastructure project is approximately 99% complete, with the city reporting a current construction cost of $885,599 versus an original contract figure cited at $924,869, yielding about $39,000 in savings.

City Engineer Barry Adams reported that the Pollard (referred to in slides also as 'Polar') Mills Phase 4 project—which included new curb, gutter, sidewalks, retaining walls, storm sewer infrastructure and a new asphalt roadway along Dixon Street—is effectively complete.

Adams said the original construction contract was listed at $924,869 and the current construction cost is $885,599, roughly $39,000 below the contract amount; staff said savings were achieved by reducing the linear footage of a retaining wall and by avoiding work on an old bridge to limit potential damages. Adams told commissioners the contractor was Southern Ohio Trenching and Excavating and the project was about 99% complete with only a handrail on the punch list.

Commissioners commented on the improvement to pedestrian access and drainage, discussed the difficulty of utility relocation during the project, and thanked staff for the work.