Board awards MSHS and bus garage roof replacement to Bell Roofing for $594,950; GEI recommends 5% contingency
Summary
GEI recommended and the board awarded the Marquette Senior High School and Auxiliary Services Bus Garage roof replacement contract to Bell Roofing Company for $594,950 and recommended a 5% contingency bringing total project authorization to $624,700. The board voted 5-0.
Get email alerts on the Roof Replacement topic
No spam. Unsubscribe anytime.
GEI Consultants recommended awarding the Marquette Senior High School and Auxiliary Services Bus Garage roof replacement contract to Bell Roofing Company following bid opening; the Board approved the award on a 5-0 vote.
GEI's March 18 recommendation noted one responsive bid from Bell Roofing Company for a base-plus-alternate total of $594,950. GEI recommended acceptance of the alternate to install the MSHS canopy roof drain outlet below grade to reduce potential for ice buildup and improve pedestrian safety. GEI advised inclusion of a 5% construction contingency ($29,750) to address unforeseen conditions, for a total project authorization of $624,700. A motion to award the contract was made by Eric Smith and seconded by Cherryl Maddox-Smith; the motion carried 5-0.