County secures $4.13M addition for Borden Tunnel, bids total $8.75M; award contingent on state concurrence

Board of County Commissioners, Allegheny County · June 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff said State Highway's Carbon Reduction Program supplied $4,132,681 in additional funding for Borden Tunnel rehab on the Great Allegheny Passage, bringing total project funding to $7,756,477; the low bid opened at $8,753,021 and award is contingent on SHA concurrence.

Public works staff told commissioners they had secured an additional $4,132,681 through the Carbon Reduction Program to cover a large shortfall for the Borden Tunnel rehabilitation on the Great Allegheny Passage. "The amount that we are receiving is $4,132,681," the presenter said.

Staff said the additional award supplements an original $3.6 million MOU and raises total available funding to $7,756,477; local match obligations of a little over $1,000,000 remain. Bids opened late May and the apparent low bid for the base work and alternates came in at $8,753,021. Staff recommended the board approve signature of the first MOU amendment and approve award contingent on State Highway Administration concurrence; commissioners voted to authorize signatures and contingent contract actions.

Why this matters: A multi-million-dollar shortfall had threatened the project; the added state funding reduces the county's local-match pressure but leaves a small shortfall and the award remains conditional on state concurrence with federal/state grant terms.