Fire station project: committee hears revised completion estimate and contingency status

Financial Planning Committee · July 31, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Financial Planning Committee received a construction update: framing and concrete floors are done, geothermal wells installed, and a certificate-of-occupancy/move-in is now projected for mid-January with final closeout in early March. Officials said MassDOT approval for a Route 20 utility crossing remains outstanding.

John Rapa gave the fire station construction update, describing framing progress, installed geothermal wells and completed concrete floors. He told the committee that detention basins and drainage piping are in place and that crews are coordinating with MassDOT to run a drainage pipe under Route 20; MassDOT approval to cut the street had not been received as of last week.

Rapa said the project team revised completion forecasts and expects a certificate of occupancy and move-in "probably mid January and a final closeout with a punch list in early March." Committee members asked about contingency exposure and learned the town is monitoring budget versus contingency but had "not rung the alarm bell" yet; staff said they expect to continue performing arbitrage calculations related to the bond spending schedule and may need additional borrowing later this year.