Williamston schools detail bond project timelines; pool to close May 1 for HVAC work
Summary
Superintendent Dr. Adam Spina told the board the Explorer final permit is imminent, WHS paving will occur after school and the district pool will close May 1–mid‑July for Pool Pak and HVAC installation as part of ongoing 2024 Bond projects.
Get email alerts on the Bond Projects topic
No spam. Unsubscribe anytime.
Dr. Adam Spina, superintendent of Williamston Community Schools, updated the board on bond-funded construction and maintenance projects, saying the final permit for the Explorer building “should arrive any day.” He told trustees the WHS paving project is scheduled to begin after the end of the school year and be completed by mid‑July.
Dr. Spina also said the district pool “will be closed May 1 – Mid‑July for installation of Pool Pak and HVAC system.” He reported the softball field still needs one truckload of infield clay and that sidewalk installation to the dugouts is weather dependent. Board members asked clarifying questions about sequencing and timelines; no formal action was taken at this meeting other than referral of items to the April 13 agenda.