Electric City cancels CenturyWest contract for Waterfront Trail amid rising costs

City of Electric City Council · July 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City council voted to end CenturyWest's contract for the Waterfront Trail after engineers reported the project estimate more than doubled; the city will ask TD&H Engineering to analyze cost, timeline and feasibility. Councilmember Don Redfield voted no.

The Electric City Council on July 8 voted to terminate the Waterfront Trail contract with engineering firm CenturyWest and direct the city's current engineer, TD&H Engineering, to analyze cost, timeline and feasibility for the lakeside pathway.

Council was told CenturyWest has done no work on the project since 2022 and provided a new construction-through-completion estimate of $1,318,251.65, with the city's share estimated at $445,842. The firm also proposed an additional geotechnical investigation fee of $55,908.35 on top of prior engineering expenses of $83,953.56.

Mayor Diane Kohout presented the updated figures and the council moved (M/S Gilbert/Martin) to cancel the CenturyWest contract and transfer evaluation duties to TD&H Engineering. The motion carried with one recorded no vote from Councilmember Don Redfield.

Councilmembers cited escalating costs and a long pause in CenturyWest's work as reasons to seek a fresh feasibility analysis. The next step is for TD&H to provide a written cost and timeline analysis; council did not set a public deadline for that report.