Council approves design contract for Crowfield restroom facility
Summary
The council approved a recommendation to hire the Middleton Group to produce 100% construction drawings for the Crowfield restroom facility so the city can proceed to construction; the motion passed by voice vote.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
Mrs. Ziegler (speaker 9) presented a recommendation to engage the Middleton Group to complete 100% drawings for the proposed Crowfield restroom facility. The contract is intended to bring the project to the construction-ready stage.
Council moved to approve the recommendation and the motion carried by voice vote. Staff said the drawings will allow the city to solicit construction bids and proceed with facility work once funding and approvals are in place.