Florence approves $79,730 final payment to Hemphill, authorizes ARPA close‑outs
Summary
The board authorized final payment of $79,730 to Hemphill Construction, accepted warranty and release of liens, and authorized Mayor Gunn to sign close‑out documents for the ARPA MCWI program.
Get email alerts on the Construction Closeout topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker recommended approval of Pay Request No. 9—Final from Hemphill Construction Company, Inc., and the board voted to issue final payment of $79,730.00, accept the contractor's warranty and release of liens, and release the contractor's certificate of deposit posted in lieu of retainage. "A Motion was made by Alderman Sistrunk, seconded by Alderman Martin to approve PAY REQUEST NO. 9-FINAL FROM HEMPHILL CONSTRUCTION COMPANY, INC. AND TO AUTHORIZE THE CITY CLERK TO ISSUE FINAL PAYMENT, IN THE AMOUNT OF $79,730.00," the minutes state; the motion carried unanimously.
The board also authorized and directed Mayor Gunn to sign any and all close‑out documents related to the ARPA MCWI program, a step City Engineer Tim Parker said was necessary to finalize that federal‑funded project. The board recorded unanimous approval on the ARPA close‑out authorization.