Topographic survey shows Mar-Oco landfill has about 164,644 cu.yds. of remaining capacity
Summary
SCS Engineers’ Jan. 12, 2026 survey found 164,644 cubic yards of available landfill space; staff estimate the site will reach capacity in roughly five years at current intake rates. Survey cost was $3,740.
Get email alerts on the Landfill Capacity topic
No spam. Unsubscribe anytime.
SCS Engineers conducted a topographic airspace survey for Mar-Oco Landfill on Jan. 12, 2026 and reported 164,644 cubic yards of remaining capacity. The committee reviewed the results during its Feb. 13 meeting.
The minutes record the survey contract cost as $3,740. Committee staff used the firm's calculation and the site's average annual intake to estimate the landfill will be full in approximately five years if current trends continue. No formal policy action was taken at the meeting; the survey information is recorded for planning and budgeting purposes.