Henderson board withholds $246,000 payment for Gene Record Park modular restroom until delivery and inspection

Board of Mayor and Aldermen, City of Henderson, Tennessee · July 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor requested $246,000 before delivery of a modular restroom facility for Gene Record Park; the board decided not to pay until the restroom is delivered and passes final inspection, with a check to be available at delivery.

The board discussed a payment request from Grinder Tabor & Grinder related to work at Gene Record Park. The contractor asked the city to pay $246,000 before delivery and setup of a modular restroom facility, but the contract specifies payment upon completion. After discussion, the board decided not to make any payment until the restroom is delivered and passes final inspection; Mayor Bell said the city will have a check on hand upon delivery and inspection.

Minutes state the contractor is currently in breach of contract by requesting payment before completion. Recorder Jim E. Garland said he had received a picture from the manufacturer and that he was working with the contractor and the engineer on project adjustments; the board scheduled no interim payments and required delivery and final inspection as conditions for payment.