Staff told the Municipal Building Authority on March 24 that operational testing of the water treatment plant is underway and progressing through key process steps.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
Board Member Jack Lytle said there was progress on the county's water treatment plant but that he had no new detailed update to present. Staff member Aaron Averett, who was listed as attending remotely, reported that testing is underway.
In the meeting record Aaron Averett said, "testing is happening. Water is following through parts of the process." No safety incidents or failures were reported during the update; the board did not take action beyond receiving the report.