NextEra tells Pratt County Ninnescah Thermal project work to begin this fall; materials arrive mid‑August

Pratt County Board of Commissioners · June 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

NextEra Energy Resources briefed commissioners that material deliveries for the Ninnescah Thermal Storage Project are expected in mid‑August, construction to begin in September, and completion anticipated by December.

Sam Nisbitt of NextEra Energy Resources told the Pratt County commission material deliveries for the Ninnescah Thermal Storage Project are anticipated to begin in mid‑August, with construction starting in September and project completion expected in December.

Nisbitt said NextEra sought to maintain open communication with county officials about project activities within Pratt County. The company did not present permits or request county action during the update; the presentation was informational.

Why it matters: the Thermal Storage Project represents local infrastructure activity that may involve county roads, deliveries and construction scheduling. County staff and NextEra will continue coordination as site work approaches.

What’s next: NextEra will proceed with the project schedule as described and notify county staff of significant activity or permit needs.