Aspen council begins pre-NEPA work to test whether a new EIS is warranted for Entrance to Aspen
Summary
City staff and Jacobs outlined a months-long pre-NEPA process to develop a concise purpose-and-need statement, gather traffic and safety data and hold stakeholder workshops — steps intended to delay the NEPA clock and test whether FHWA/CDOT will agree a new EIS is needed.
Get email alerts on the Nepa topic
No spam. Unsubscribe anytime.
City officials and Jacobs consultants used the Aspen City Council work session on Dec. 16 to launch a pre-NEPA phase that would develop a purpose-and-need statement and assemble the technical data needed to determine whether to request a new environmental impact statement (EIS) for the Entrance to Aspen corridor.
A Jacobs presenter told the council the pre-NEPA work will include traffic and safety analyses, an origin–destination study and targeted stakeholder outreach, with the goal of refining a short, digestible purpose-and-need statement for FHWA and CDOT. "[CDOT and FHWA] said it would require a strong purpose and need that's backed up by the data," the Jacobs presenter said during the session.
Staff emphasized that the pre-NEPA effort is intended in part to delay the formal two-year NEPA clock. The presenter explained that recent NEPA guidance requires EIS work be completed in two years once a Notice of Intent is issued, and doing upfront studies and public engagement can help the city meet federal timelines if it chooses to initiate a new EIS.
Council members pressed Jacobs on what changes to the previously adopted preferred alternative would trigger a new EIS. Jacobs said certain alternatives (for example a three-lane shifted or split-shot alternative) would likely require a new EIS and that CDOT/FHWA — not the council — would make the final call on whether a new EIS is warranted, after reviewing a data-driven purpose and need.