Police Jury approves Change Order reducing New Public Works Facility contract to $840,000, extends time to 180 days
Summary
The Police Jury approved Change Order No. 1 for the New Public Works Facility, reducing the contract value from $922,220.00 to $840,000.00 and extending completion time from 120 to 180 days.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Police Jurors on June 23 approved Change Order No. 1 and the contract agreement for the New Public Works Facility. The motion, made by Police Juror Ryan Byrd and seconded by Police Juror Willie Morgan, recorded a change in contract value from $922,220.00 to $840,000.00 and an increase in contract time from 120 days to 180 days; the motion carried unanimously.
The minutes do not record detailed discussion of the reasons for the price reduction or the time extension, nor do they identify the contractor by name in the entry. The parish did not record any alternate motions or conditions attached to the approval in the minutes.