Valley Street project invoiced $280,739; contractor to start mid‑summer after erosion reported

Ward County Water Resource Board · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

HDR reported $280,739.11 has been invoiced on the Valley Street project out of a $426,715.00 total; Excavating Inc. plans to start mid‑summer with anticipated completion in October after a reported five‑foot erosion event at the site.

HDR reported that $280,739.11 has been invoiced on the Valley Street project so far against a total project cost of $426,715.00. Engineers noted an additional five‑foot erosion caused by recent rainfall at the site.

Excavating Inc. still plans to begin work mid‑summer and expects overall completion in October. The update was recorded as an engineering progress report; no formal Board action was recorded beyond receiving the status report.