Suffield Town Meeting Authorizes $11.67M Road Improvements Bond for Bridges, Phelps Road
Summary
Voters at the Special Town Meeting approved an $11.67 million bond authorization for road and bridge work, including replacement of multiple culverts and a planned reconstruction of Phelps Road after engineering cores found insufficient pavement thickness and base material.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
The Town Meeting voted to authorize an $11,670,000 appropriation and related bond issuance to fund the 2026 Road Improvements Project, which covers multiple culverts and bridges and the full reconstruction of Phelps Road.
Presentation materials reviewed by the meeting identified six structures needing near-term replacement (Copper Hill Road, Suffield Street, Hickory Street, Spruce Street, River Boulevard, Boston Neck Road) with individual cost estimates (ranging from about $1.08 million to $2.5 million). The packet cited engineering findings by Barton & Loguidice indicating advanced deterioration, scour, and structural deficits at several sites. The slides state the Town will apply to the State/Local Bridge Program (SLBP) for up to 50% reimbursement and to the Transportation Rural Improvement Program (TRIP) for other eligible locations; the Phelps Road reconstruction was described separately with an estimated cost of $2,000,000 and potential TRIP funding that could cover up to 100% of construction costs.
The packet summarized the Phelps Road geotechnical findings: pavement thickness in places was only 2.5 inches (Town spec is 4 inches), base material was largely sand with little gravel, and groundwater intrusion had affected pavement performance. The town plans additional core sampling, completion of design work, and an RFP schedule aiming for construction in mid–late 2026 if grants and procurement align.
Town Clerk Michele Urch presented the bond motion; the minutes record no public comment on the road bond and that the motion passed unanimously by voice vote. The packet also detailed project timelines and grant application windows (SLBP rounds in 2026–2027 for various structures) and noted the Town completed an RFP for engineering services in January 2026 and will proceed with design selection and grant applications this spring.