County previews $1.16 million drainage improvement for Valley Center development; county to cover half

Sedgwick County · September 6, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A drainage improvement for the Harvest Place Phase 1 development in Valley Center is on the consent agenda; the project cost is about $1,157,427 and Sedgwick County would be responsible for 50% of funding, paid over three years per the CIP.

Mayor Stolitz previewed a consent-agenda item for a drainage improvement around the Harvest Place Phase 1 development in Valley Center and said the county's share would be roughly half of the project cost.

"The county is responsible for 50% of that funding in that project when it goes forward, which runs at about 1.157, dollars 1,100,000," Mayor Stolitz said; later he clarified the dollar figure as $1,157,427. County staff added the amount will be paid over a three-year schedule with the first installment due this year and payments for 2025 and 2026 already approved in the capital-improvement program (CIP).

Mayor Stolitz also noted an associated capital-improvement amendment (Item K) will accompany the consent item when it appears on next Wednesday's agenda. No formal vote was taken at the agenda review; the item is slated for the consent agenda.