Commissioners award $114,320 for targeted Detention Center roof repairs
Summary
The board awarded the Detention Center Roof Repair project to Skyline Construction Services for $99,320 with a $15,000 contingency (total $114,320), funded by 2018 SPLOST; completion expected in 90 days.
Get email alerts on the Infrastructure Repairs topic
No spam. Unsubscribe anytime.
Houston County commissioners on June 2 approved awarding a targeted roof-repair contract for the Detention Center to Skyline Construction Services, Inc. of Milledgeville for $99,320 and authorized a $15,000 contingency, bringing total project authorization to $114,320. The Board recorded that this is a 2018 SPLOST-funded project, and the contractor is expected to complete the repairs within 90 days of approval.
Commissioner Talton said the approved repairs are intended to extend the life of a portion of the jail roof until a larger 2024 SPLOST-funded replacement can be scheduled. The Board approved the award unanimously.