County outlines Bridge 95, guardrail grants and procurement timeline; CCMG, federal aid summarized

Daviess County Commissioners · February 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway Supervisor Chris Winkler told commissioners the county won three grants in 2025 including an 80% federal/20% local Bridge 95 project (about $2.7M) and a 90% federal/10% local guardrail safety grant; he said RFPs were issued and consultant contracts must be in place by Aug. 1 to access funds.

Chris Winkler, Daviess County Highway Supervisor, briefed the commissioners on a package of state and federal grants that the highway department secured in 2025 after unsuccessful 2024 applications. He said the Bridge 95 project carries an 80% federal / 20% local split for an estimated $2.7 million project, and the guardrail work is a safety grant at 90% federal / 10% local.

Winkler also summarized broader grant receipts: "Daviess County has received a little over $10 million at a 20% match meaning the county has paid $2 million and received $8 million in grant funding from the CCMG grant," and the county has received roughly $12 million in federal aid and safety funds with varying match percentages. He said RFPs have been sent, Letters of Interest will go to a scoring committee, and the county must be under contract with a consultant by Aug. 1 to secure the funds.