Highway supervisor: Runaround Road about 90–95% done; commissioners seek March 10 completion update
Summary
Daviess County Highway Supervisor Chris Winkler told commissioners the Runaround Road project is roughly 90–95% complete but not yet reconnected; commissioners asked for a March 10 completion date and for staff to appear at that meeting to explain delays.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Chris Winkler, Daviess County Highway Supervisor, told the Daviess County Commissioners on Feb. 24 that the Runaround Road project remains unfinished and is approximately "90-95% completed" but has not been reconnected to the county road.
Winkler said the department has had trouble sourcing the correct stone and was set back by a recent snowstorm; he also said the county has held off releasing the project bonds until the work is complete. "the runaround road is not completed yet," Winkler said. Secretary Nathan Gabhart asked for a firm completion date of March 10, 2026, and requested that highway staff appear at the March 10 meeting to explain the remaining work and schedule.