Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Spending topic

No spam. Unsubscribe anytime.

Commissioners approve firewalls, change orders for counseling facility and public works project

Board of County Commissioners of Sweetwater County · August 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a $124,086.50 purchase to replace end‑of‑life Cisco firewalls (hardware and professional services), a $330,000 change order to complete site work at the Southwest Counseling Jonah facility (county contributing $80,000), and a time‑only change order extending the Public Works combined facility substantial completion to Sept. 24, 2025.

Commissioners approved a series of capital and contract items that the county said were necessary to complete ongoing projects and to replace aging equipment.

IT Director Tim Knight recommended replacing end‑of‑life Cisco firewalls and proposed buying hardware from Advanced Networking Management for $108,009.02 plus shipping and contracting professional services from 954 Consulting for $15,160. "A and M piece would be the hardware... which would include all the firewalls licensing... for $108,009.02," Knight said; commissioners approved the combined purchase (totaling $124,086.50 plus shipping) and noted it was under the budgeted capital amount of $145,000.

Public Works Director Gene Magerski described Change Order #1 to the Southwest Counseling Jonah facility (Harper Grant HHS‑1127): the county added site work and paving back into the scope to maximize the grant and will contribute $80,000 to reach the grant threshold so the facility can be occupied. Commissioners approved the $330,000 change order. Magerski also described a single time‑only change order on the Sweetwater County Public Works Combined Facility to extend substantial completion from Aug. 15, 2025 to Sept. 24, 2025; commissioners approved that extension. The board authorized the chairman to sign necessary documents for the change orders.