Great Hill Fire Tower restoration progresses; paint reimbursement tabled
Summary
Restoration of the Great Hill Fire Tower is underway with about two-thirds of the tower steel ground and primed; commissioners tabled a $232.92 reimbursement for paint until the order is finalized and any returns are confirmed.
Get email alerts on the Great Hill Fire Tower topic
No spam. Unsubscribe anytime.
Chair Ned Beecher reported that approximately two-thirds of the Great Hill Fire Tower steel has been ground and primed and that restoration work is making good progress; final paint was expected to arrive later in the week. The minutes log the progress as part of the Managed Lands & Trails and announcements sections.
A reimbursement request for $232.92 in Great Hill fire tower paint was tabled until the next meeting to allow for any necessary returns or adjustments once the paint order is complete. Commissioners will revisit the reimbursement after the paint order is verified.