Staff reports progress on airport water and sewer line project, pump station remains schedule-critical

Whiteville City Council · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said crews are installing piping and electrical infrastructure on the airport water and sewer line project and expect the pump station to determine the project schedule; staff expect budget numbers and a balanced draft budget ready by the next meeting.

Staff updated the council on the airport water and sewer line project, reporting regular on-site activity and an anticipated timeline.

"They're putting down piping and boxes and electrical boxes and so on and so forth, and they are working out there every day," staff said, adding that the pump station is the critical item likely to control the schedule. Staff expressed optimism that work will proceed rapidly and said they expect to have budget numbers and a balanced draft budget for council review at the next meeting.

The update was informational; no procurement or contract action is recorded in the transcript excerpt.