Farmingdale updates on GAC/AOP well work, testing costs and funding commitments totaling $1.5M
Summary
Staff reported sampling and testing for AOP/GAC at Wells 1–3, a steel building for GAC tanks nearing completion, additional testing costs of about $16,000 per well, a $1 million county commitment (half received), and a $1.1 million federal commitment communicated by Congressman Suozzi in the 2025/2026 federal budget.
Get email alerts on the Water Quality topic
No spam. Unsubscribe anytime.
Water Department staff reported that sampling and testing at Wells 1–3 for the AOP/GAC installation continues and that Well 1–3 is now fully operational as the lead well. A new steel building to cover the GAC tanks at Well 1–3 was under construction with an expected finish around Nov. 15, 2024, and staff noted additional testing costs of approximately $16,000 per well for newly monitored contaminants.
PRI is developing a master schedule for completion of all wells (expected by May 1, 2025). The minutes record a committed $1 million through County Legislator John Ferretti to offset costs for the new water treatment systems, with $500,000 already received, and that Congressman Thomas Suozzi informed the Village of a $1.1 million commitment in the 2025–2026 federal budget (described in the minutes as not a reimbursement grant). Staff also reported work on WIIA grant status, evaluation of a ground tank roof and D&B analyses related to tank and antenna work, and the purchase of NSF/ANSI‑certified Brita pitchers for customers with galvanized services as part of Lead and Copper outreach.