WES updates West Linn on Clackamole outfall project, proposes modest 4.9% rate increase

West Linn City Council · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Clackamas Water Environment Services told the West Linn council its Clackamole outfall—a $58 million project to move the Tri‑City discharge to a deeper river location—remains on time and on budget. WES proposed a 4.9% rate increase for 2025–26, described as roughly $1.45 per month for a typical West Linn account.

Clackamas Water Environment Services Director Greg Geist gave the West Linn City Council an overview of the utility’s operations and capital priorities, saying WES treats roughly 7,000,000,000 gallons of wastewater a year and aims to deliver predictable, long‑term rates.

Geist highlighted the Tri‑City outfall project—nicknamed “Clackamole”—as a multi‑year environmental effort to move the primary discharge to a deeper section of the river and equip it with an 18‑riser, 90‑inch diffuser intended to improve dilution and protect fish habitat. Construction began in July 2024; tunneling finished in December 2024; diffuser installation was scheduled for July–October 2025. Geist said the Clackamole project is currently on time and on budget and that total project cost is $58,000,000.

On rates, Geist said WES is committed to “reasonable and predictable” increases and proposed a 4.9% price change for fiscal 2025–26. He described that change as about "$1.45 a month, about $18 a year" for a West Linn household. Council members asked how the utility plans to revisit charges as growth or master‑plan assumptions change; consultants and staff said SDCs and master plans are the usual triggers for recalculation.

The presentation covered other capital work affecting West Linn, including a Willamette pump station replacement and force‑main project to relocate an aging station out of the floodplain, upgrades to primary clarifiers and aeration basins, and planned influent pump‑station modernization. Geist noted WES produces roughly 40% of its facility energy needs, recently achieved a 4.1% energy reduction and received a $44,000 incentive for efficiency measures.

Councilors thanked WES for outreach and asked about sharing the project video and arranging tours; Geist said staff will make materials available and invited council tours and additional neighborhood briefings.